1. Introduction
Purpose of this Statement
1.1. This Statement of Consultation has been prepared to comply with Regulation 22 (1)(c) of the Town and Country Planning (Local Planning) (England) Regulations 2012, which states:
Submission of documents and information to the Secretary of State
22.(1) The documents prescribed for the purposes of section 20(3) of the Act are—
(a) the sustainability appraisal report;
(b) a submission policies map if the adoption of the local plan would result in changes to the adopted policies map;
(c) a statement setting out—
- (i) which bodies and persons the local planning authority invited to make representations under regulation 18,
- (ii) how those bodies and persons were invited to make representations under regulation 18,
- (iii) a summary of the main issues raised by the representations made pursuant to regulation 18,
- (iv) how any representations made pursuant to regulation 18 have been taken into account;
- (v) if representations were made pursuant to regulation 20, the number of representations made and a summary of the main issues raised in those representations; and
- (vi) if no representations were made in regulation 20, that no such representations were made;
(d) copies of any representations made in accordance with regulation 20; and
(e) such supporting documents as in the opinion of the local planning authority are relevant to the preparation of the local plan.
1.2. It sets out how the Authority has undertaken community participation and stakeholder involvement in the production of the New Forest National Park Local Plan Review in accordance with the Town & Country Planning (Local Planning) (England) Regulations 2012, the Statement of Community Involvement (SCI) and Local Development Scheme (LDS) in place at the time.
1.3 This statement should be read in conjunction with the Local Plan Reg 18 (Part 1) Consultation Statement (November 2025), which summarises consultation undertaken during February – March 2025 on the Strategic Direction of Travel document. Further consultation was undertaken on a full draft local plan during November – December 2025 as set out in the Local Plan Reg 18 (Part 2) Consultation Statement (August 2026).
1.4 This statement therefore reflects consultation under Regulation 19, on the pre-submission draft Local Plan Review for six weeks, between 17 August and 30 September 2026. Accordingly, this statement summarises the consultation process, comments received and how the Authority has responded to the main issues raised, prior to submission of the Local Plan Review for examination.
Background
1.5 The New Forest National Park Authority undertook a review of the planning policies set out in the New Forest National Park Local Plan 2016–2036, adopted in August 2019, to determine whether they needed updating. This assessment was due by August 2024 (5 years from the date of adoption) and was in response to changes in national policy and the experiences of applying the adopted planning policies for the past five years. However, it is important to emphasise that many key aspects of national planning policy, guidance and law relating to National Parks remain unaltered from the time the Local Plan was prepared, examined and adopted. Therefore, the Authority has undertaken a review of the Local Plan rather than preparing a completely new Local Plan. At the Authority Meeting on 21 March 2024 (report AM 675/24), members to a review of the adopted Local Plan.
1.6 The revised Local Plan will form a key part of the statutory ‘development plan’ for the National Park and to guide decisions on planning applications submitted. The Local Plan sets out detailed planning policies and allocations that seek to deliver the two statutory National Park purposes and related socio-economic duty, together with the Protected Landscape Duty, which requires that relevant authorities ‘seek to further’ the statutory purposes.
Duty to Cooperate
1.7 The “Duty to Cooperate” was introduced by Section 33A of the Planning and Compulsory Purchase Act (2004). Section 110 of the Localism Act (2011) reinforces the duty to cooperate as per Section 33A, in relation to the planning of sustainable development. It places a legal duty on Local Planning Authorities, County Councils and prescribed public bodies to engage constructively, actively, and on an ongoing basis to maximise the effectiveness of a local plan in the context of strategic cross boundary matters.
1.8 On 25 March 2026, through the Levelling-up and Regeneration Act 2023, the formal duty was abolished, however, there remains a requirement for Local Planning Authorities to cooperate and engage on cross boundary issues.
1.9 Engagement has taken place to date with both neighbouring local authorities and the prescribed bodies. Further details are set out in the Cooperation Statement and agreed Statements of Common Ground published separately to this report on the examination webpage.
2. Overview New Forest National Park Local Plan Review Timeline
2.1 The Local Plan Review has been developed through several consultation stages supported by early and ongoing engagement with communities, businesses and organisations, ensuring the final strategy and policies reflect the needs of the New Forest National Park.
2.2 The table below summarises the key plan preparation and consultation stages undertaken in the development of the Local Plan Review prior to its submission in December 2026.
| Key stages of the Local Plan preparation prior to submission for examination | Key dates | Summary |
|---|---|---|
| Resolution made to undertake a Local Plan Review | March 2024 | The decision to undertake a partial review of the Local Plan was made during the Authority Meeting on 21 March 2024. |
|
Review of the Local Plan adopted 2019, commissioning of new evidence studies, and preparation of a draft Local Plan Authority meeting 25 July 2024 agreed to update LDS (report AM 684/24) |
March 2024 to January 2025 | Review of existing policies and evidence; commissioning of updated evidence and further research to inform the Local Plan Review. |
|
Regulation 18 Part 1 Strategic Direction of Travel Consultation & Call for Sites Authority meeting 23 January 2025 agreed to consultation on the Direction of Travel Document (report AM 702/25) |
February to March 2025 |
Public consultation on the key issues and options took place over a 6-week period in early 2025. Four drop-in events were held, and a questionnaire was produced and made available to statutory consultees, stakeholders and residents. A ‘Call for Sites’ was also undertaken, inviting local communities, landowners and developers to put forward sites for consideration for residential; employment; and Gypsy, Traveller & Travelling Showpeople development, among other uses. |
| Consideration of Reg.18 (Part 1) representations & technical evidence, with amendments to the draft Local Plan | April to October 2025 | Representations to the Part 1 consultation were reviewed, alongside evidence from technical studies & Duty to Cooperate meetings. A draft Local Plan was prepared. Further technical studies were commissioned. |
| Stage | Key dates | Summary |
|
Regulation 18 Part 2 Draft Local Plan Consultation Authority meeting 16 October 2025 agreed to consultation on the draft Local Plan (report AM 727/25) |
November to December 2025 |
Public consultation on the draft local plan took place, evidence studies and supporting documents were also published. An online consultation platform was used to receive representations. The consultation ran for 6 weeks in late 2025 and included 5 drop-in events and an online presentation with a Q&A session. |
| Consideration of Reg.18 (Part 2) representations & amendments to draft Local Plan | January to July 2026 |
Comments from the second consultation were reviewed, alongside evidence from Duty to Cooperate meetings and completed evidence studies. The draft Local Plan was accordingly amended to reflect representations where justified. |
|
Regulation 19 Pre-Submission Consultation Authority meeting 23 July 2026 agreed to LDS update and consultation on the Regulation 19 draft Local Plan (report AM 740/26) |
August to September 2026 |
Consultation was undertaken on the revised local plan and its evidence base over the course of 6 weeks. This included 6 drop-in events and an online presentation with a Q&A session. An online consultation platform was used to publish the consultation documents and to receive representations. |
|
Preparation of submission to Secretary of State Authority meeting 27 November 2026 agreed to submit the Local Plan Review for examination |
October to November 2026 | The NPA reviewed the comments received during the Regulation 19 consultation. It is the National Park Authority’s view that the draft Local Plan meets the legal requirements, is sound, and is ready to be submitted for Independent Examination, which was agreed at the Authority meeting on 27 November 2026. |
| Submission to Secretary of State for examination (Reg.22) | December 2026 | The final draft of the Local Plan and supporting documentation including a schedule of proposed modifications for consideration through the examination was submitted to the Secretary of State in December 2026. |
3. Part 3 Regulation 19
3.1 Prior to commencement of the consultation, presentations providing an update on the Local Plan were delivered to NPA members (on 24 February, 15 April, 11 June 2026). These sessions set out the responses to the previous Regulation 18 Part 2 consultation and provided detail on where and how the Local Plan had evolved in light of feedback. Through these sessions members could recognise the concerns of the community and continue to incorporate local issues into developing planning policy.
3.2 Updates were also provided at Parish Quadrant meetings, the New Forest Consultative Panel, and New Forest Access Forum meetings in the first half of 2026.
3.3 Approval was given during the Authority meeting on 23 July 2026 for publication of the Regulation 19 Submission draft Local Plan review for consultation.
3.4 The Regulation 19 consultation on the Proposed Submission Local Plan Review was undertaken for 6 weeks between 17 August - 30 September 2026.
3.5 The Regulation 19 representation period is the last stage of public engagement before submitting the draft plan to the Planning Inspectorate for examination. This is a formal process that requires comments on the soundness and legal compliance of the plan.
Summary of Engagement
3.6 Publication of the Proposed Submission local Plan Review was sent to all those specific and general consultation bodies (211 recipients) as prescribed by planning regulations (Appendix A), in addition to those registered within the National Park Authority to receive its Enews which has 27,000 subscribers. Details were supplied of when and where documentation would be publicly available to view, and how representations could be submitted.
3.7 Consultation was promoted through a number of channels including press releases; media coverage; e-newletters, social media and posters were displayed across the National Park as set out in Appendix B. A formal public notice was also published in the Lymington Times and New Milton Advertiser for one week – see Appendix C.
3.8 A Statement of Representations Procedure was duly published setting out the subject matter and area covered; the consultation period; where to view documents and how to make a representation. The Authority’s data protection policy and privacy notice were also highlighted in terms of how the representations submitted would be processed and subsequently published.
3.9 The draft Local Plan and key supporting information were available for inspection at the Authority’s office during normal office hours in Lymington Town Hall, Avenue Road, Lymington, SO41 9ZG; and online at: Local Plan review 2025-27 - New Forest National Park.
3.10 An online presentation was held via Microsoft Teams on Thursday 10 September 2026, between 4pm – 5.30pm.
3.11 The presentation was also delivered during several in-person public drop-in events (2pm – 7pm) that were held across the National Park to enable people to speak to planning staff and find out more about the Local Plan review.
3.12 All drop-in sessions were structured as follows:
- 2pm-5pm - view the display boards and chat informally with National Park Authority officers about the revised draft Local Plan.
- 5.30pm - presentation explaining the key changes since the 2025 consultation and the next steps for the Local Plan, followed by a managed Q&A session.
| Location | Date | Approximate number of attendeees |
|---|---|---|
| Landford Village Hall | Wednesday 2 September 2026 | 45 |
| Bartley Village Hall | Friday 4 September 2026 | 29 |
| The Copythorne & District Royal British Regional Hall | Monday 7 September 2026 | 39 |
| Jubilee Field, Sway | Tuesday 8 September 2026 | 36 |
| Lyndhurst Community Centre | Friday 11 September 2026 | 16 |
| Redlynch Village Hall | Wednesday 16 September 2026 | 35 |
3.13 Representations could be submitted via:
- the online consultation portal, or
- email to policy@newforestnpa.gov.uk, or
- posted to the Policy Team, New Forest National Park Authority, Lymington Town Hall, Avenue Road, Lymington, SO41 9ZG.
Consultation Responses – Overview
3.14 When submitting representations, respondents were asked whether they believed the draft Local Plan Review, in whole or in part, to be sound and legally compliant. Respondents were also given the opportunity to provide comments and to propose modifications. The majority of comments were submitted through the Authority’s online consultation portal Commonplace, with some responses also being sent by email and letter, these have since been uploaded to Commonplace to enable the following analysis.
3.15 All responses can be viewed in full at New Forest National Park Authority Local Plan Examination - New Forest National Park
3.16 Representations were received from over 300 different organisations, groups and individuals, of these responses some 749 comments were made. Figure 1 below summarises the breakdown of representations per chapter:
Figures 2 and 3 below summarise1 legal compliance and soundness:
1 Not all representations responded to these questions
3.17 As the data above illustrates, Chapter 4 and 8 generated the most feedback, commenting on the spatial strategy and associated site allocations.
4. Summaries of Representations and Key Issues
4.1 Assessment of the representations reveals the following key issues raised through the Regulation 19 consultation:
Key Issues Raised
- Concerns raised regarding the draft Local Plan’s approach of not meeting the identified housing needs arising within the National Park in full and the potential impact on the socio-economic well-being of communities within the National Park.
- Representations on whether the proposed spatial strategy (draft policy SP3) is the most appropriate. This includes representations objecting to the proposed settlement hierarchy and the identification of the smaller defined villages; as well as representations promoting sites on the edge of the National Park (adjacent to larger settlements outside the National Park) in meeting identified development needs.
- Local community opposition to the proposed site allocations (for housing and travelling showpeople use) citing impacts on road infrastructure and the lack of public transport opportunities; impacts on landscape character and protected habitats; lack of infrastructure (primarily health and education); loss of local distinctiveness; and the risk from increased flood risk.
- The relevant landowners confirm that the proposed site allocations are available and deliverable within the Local Plan period.
- Concerns that the majority of the identified employment needs are proposed to be met in a single allocation, rather than being distributed on sites across the area.
- Representations seeking greater encouragement for the provision of larger renewable energy schemes, rather than focus on small-scale proposals
- Expressions of support for the proposed ‘principal residency condition’ for new open market housing; and the local connection criteria for new affordable housing to ensure development meets needs arising within the National Park.
- Representations from some landowners and developers regarding the proposed retention of the existing floorspace limit for net new dwellings (draft policy SP31), the proposed introduction of the ‘principal residency condition’ and the proposed affordable housing targets (draft policy SP42).
Sustainability Appraisal & Habitats Regulation Assessment
4.2 Throughout the plan making process the Authority has engaged with the environmental agencies (Natural England, Historic England and Environment Agency), particularly in respect of their roles with the Sustainability Appraisal and Habitat Regulations Assessment. The following table summarises their representations on the Regulation 19 Local Plan:
| Organisation | Response to Reg 19 | NFNPA response |
|---|---|---|
| Natural England |
Natural England welcomes the strong engagement with the New Forest National Park Authority and the positive consideration given to their feedback to the Draft Local Plan. Natural England considers the Local Plan to be sound. Site Allocations for C2 use – suggest that mitigation requirements are clarified for consistency. Alternative Greenspace and references to Strategic Access Management and Monitoring to be referred to in the local plan or in a Statement of Common Ground. Habitat Regulations Assessment – satisfied that given the quantum of housing proposed the mitigation measures remove adverse effects on integrity of the designated sites. |
Comments welcome and support noted. Proposed Modification PSM17 addresses the point made in terms of C2 uses and urban edge impacts. Statements of Common Ground have been prepared with key partners and refer to this matter where relevant. Noted and welcomed. |
| Historic England | Welcome the inclusion of policies for the historic environment which meet the obligation for preparing a positive strategy as required by the NPPF. The key test of the soundness of the plan and the achievement of sustainable development as defined in the NPPF in respect of the elements that relate to the historic environment (paragraph 196) have been met. | Noted and welcomed. |
| Environment Agency |
No comments to make regarding soundness or legal compliance as the Plan is comprehensive in nature and covers matters within our remit to a satisfactory standard. Number of minor comments made in support of amendments to policies in response to Reg 18 comments. Request that the evidence base should include the results of the Sequential Test, to accord with national policy. |
Noted and welcomed. Noted A Sequential Test has been completed and published as part of the evidence base for the local plan. |
4.3 The following table summarises those representations which made specific reference to the Sustainability Appraisal/Strategic Environmental Assessment, with a focus on the spatial strategy options tested as reasonable alternatives:
| Respondent | Main Issues Raised | How the representations have been taken into account |
|---|---|---|
| Luken Beck (obo Seaward Properties) |
The SA considers a number of reasonable alternatives for accommodating growth within the National Park, including Option E, which would involve the allocation of land around the periphery of the National Park on sites related to settlements outside the Park boundary. Seaward Properties does not suggest that all land adjoining settlements outside the National Park should be regarded as suitable for development. However, concern is raised that the appraisal of Option E adopts a high level and broad-brush assessment which does not sufficiently distinguish between different types of peripheral site. The SA does not fully consider the distinction between dispersed peripheral growth across a wide range of locations; and carefully selected sites adjoining the most sustainable settlements outside the National Park boundary. The appraisal itself identifies significant strengths associated with Option E, including its performance in relation to housing delivery, community outcomes and economic objectives. Given the scale of unmet need that remains under the preferred strategy, it is considered that the Sustainability Appraisal should give greater consideration to whether a more targeted form of Option E, focused on carefully selected sites adjoining sustainable settlements such as Lymington and Pennington, could contribute towards meeting housing needs without undermining the statutory purposes of the National Park. Similarly, the Authority should consider whether a blended approach drawing upon elements of both Option B and Option E would provide a more balanced strategy. It is acknowledged that a refined peripheral growth strategy would not necessarily achieve the full level of housing delivery associated with Option E as assessed through the Sustainability Appraisal. However, a targeted approach focused on a limited number of well-contained sites adjoining the most sustainable settlements outside the National Park boundary could make a meaningful contribution towards identified housing needs. For these reasons, we consider that further review of the Sustainability Appraisal and the reasonable alternatives underpinning the spatial strategy is warranted before the Plan can be regarded fully justified. |
This representation on behalf of Seaward Properties raises very similar points to the representations made on behalf of Pennyfarthing Homes, Taylor Wimpey and Gervis Property. The Authority’s view is that the SA/SEA of the draft Local Plan is required to consider ‘reasonable alternatives’ and the representation recognises that that has been done (which is welcomed). Our view is that the SA assessment is not required to assess every possible permutation and option, and the SA of the Regulation 19 Local Plan already considered a meaningful range of realistic options (given the focus of national planning policy on small-scale development to meet the needs arising from local communities within the National Park). The SA/SEA of the Regulation 19 Submission draft Local Plan considered a range of ‘reasonable alternatives’ to meet identified housing needs within the context of a nationally-protected landscape. This included a ‘blending’ of several options and the fact that 8 different scenarios were assessed is considered reasonable. At this stage the Authority does not believe there is a need for additional SA/SEA work on reasonable alternatives, as options HO1 – HO8 in the Regulation 19 Local Plan SA/SEA meet the needs of the regulations and are pitched at the appropriate level for the Local Plan-making process. |
| Respondent | Main Issues Raised | How the representations have been taken into account |
|---|---|---|
| Boyer Planning (obo Taylor Wimpey) |
It is considered that Growth Option HO5 provides the most suitable growth strategy for NFNPA to deliver the necessary housing and employment in the next plan period whilst having regard to the relevant Sustainability Appraisal themes. Option HO5 adds to Option HO2, incorporating housing adjacent to settlements around the periphery of the National Park which would include Ringwood. It is considered that with suitable policies to address any environmental pressures, Option HO5 could suitably manage and protect the landscape character and ecological connectivity in order to address any potential issues with a higher level of growth. Growth option HO5 should be re-assessed as a preferred growth option, with the addition of land at Nouale Lane as an allocation for residential development or habitat mitigation within the draft Plan. Taylor Wimpey recognises the SA has assessed alternative growth strategies. However, the concern is whether the assessment and reasons for selection adequately address the potential contribution of all sites and their individual circumstances. The requested modification is a reassessment of that opportunity, with the resulting housing provision and allocations reflected in Policies SP3 & SP29 where supported by the evidence. The potential for environmental mitigation at Nouale Lane should also be assessed on its own merits. There has been no robust assessment of the 40 homes per annum figure (or alternatives) in either the SA or other supporting evidence. It is our view that this level of housing provision is insufficient and needs to be increased. This can be secured without harming the overarching aims of the Park or resulting in unrestricted growth by utilising Towns surrounding the authority, such as Ringwood, to bolster the much needed housing provision. |
This representation on behalf of Taylor Wimpey raises very similar points to the representations made on behalf of Seaward Homes, Pennyfarthing Homes and Gervis Property. As outlined above, the assessment of reasonable alternatives needs to factor in the Authority’s legal duty to foster the socio-economic well-being of communities within the National Park. Large settlements like Ringwood and Lymington were consciously left out of the boundary of the New Forest National Park and this is relevant to the consideration of reasonable alternatives to meeting housing needs. At this stage the Authority is not convinced of the need for additional SA/SEA work on reasonable alternatives, as options HO1 – HO8 in the Regulation 19 Local Plan SA/SEA meet the needs of the regulations and are pitched at the appropriate level for the Local Plan-making process. |
| Turley (obo Pennyfarthing Homes) |
The SA that accompanies the draft Plan includes a reasonable alternative growth option (HO5) that encompasses growth around the main towns abutting the National Park. However, the ranking of outcomes against SA objectives is counterintuitive to the conclusions drawn. Turley have outlined soundness concerns under the positively prepared, justified and consistent with national policy tests. Further opportunities to meet more of the area’s unmet needs for housing, particularly affordable housing should be explored, before finalising the housing requirement, spatial strategy and land supply designations. The SA should be revisited, and suitable opportunities to meet further needs, where consistent with the framework read as a whole, be explored through main modifications. |
This representation on behalf of Pennyfarthing Homes raises very similar points to the representations made on behalf of Seaward Properties, Taylor Wimpey and Gervis Property. The representation from Turley (on behalf of Pennyfarthing Homes) misrepresents the conclusions of the SEA/SEA assessment of options – option HO5 involves a higher level of development than options HO1 and HO2 and this is why the assessment concludes that transport and climate change impacts will increase. At this stage the Authority does not believe there is a need for additional SA/SEA work on reasonable alternatives, as options HO1 – HO8 in the Regulation 19 Local Plan SA/SEA meet the needs of the regulations and are pitched at the appropriate level for the Local Plan-making process. |
| Black Box Planning (obo Gervis Property) |
The Regulation 19 Sustainability Appraisal (SA) (July 2026) appraises eight housing growth options (HO1 – HO8). This includes Option HO5, which combines the preferred strategy (Option HO2) with around 200 dwellings on land within the NPA’s adjoining settlements outside it. Although Option HO5 is recognised as a reasonable alternative, the SA does not demonstrate that the preferred strategy is justified The options exclude sustainable villages which straddle the boundary. No option considers proportionate growth at a village whose community lies partly within the Park. Bransgore falls between the two categories and is not captured by either. The SA has not appraised the clear reasonable alternative of the preferred strategy supplemented by proportionate growth at sustainable boundary villages, including Bransgore. It has not explained why Option HO5 was rejected, meaning the NPA cannot demonstrate that the preferred strategy is the most appropriate when considered against the reasonable alternatives, as required by the ‘Appropriate’ test of soundness. |
This representation on behalf of Gervis Property raises very similar points to the representations made on behalf of Pennyfarthing Homes and Taylor Wimpey. The village of Bransgore was excluded from the boundary of the New Forest National Park when the final boundary was confirmed in 2005. It does not ‘straddle the boundary’ – the main built elements of the village were all excluded from the legally established boundary. We do not agree that there should be a ‘Bransgore option’ as it is already adequately covered by option HO5. At this stage we do not believe there is a need for additional SA/SEA work on reasonable alternatives, as options HO1 – HO8 in the Regulation 19 Local Plan SA/SEA meet the needs of the regulations and are pitched at the appropriate level for the Local Plan-making process. |
| Hampshire County Council |
Hampshire County Council supports the Submission Draft Local Plan objective of strong and distinctive local communities and acknowledges that the Growth Strategy Option B (as selected from the Sustainability Appraisal Report) addresses this, by considering controlled development in existing defined villages and newly defined villages based on service provision. The objective of sustaining the vitality and viability of smaller settlements is acknowledged. The County Council acknowledges the planned growth across the National Park within the plan period is relatively modest (including a total of 285 dwellings across the allocated sites). The Plan’s evidence does not robustly demonstrate however that the proposed site locations are accessible in terms of sustainable transport options. Whilst the County Council recognises that the scale of development may not justify the preparation of a full Transport Assessment, the absence of a proportionate assessment of the likely transport impacts means that the evidence is not adequate in demonstrating that the proposed growth can be accommodated without adverse effects on the transport network or an increase in car-dependent travel patterns. |
The National Park Authority has prepared a Transport Topic Paper on the transport and accessibility issues raised by Hampshire County Council in their representations. The site assessment process considered proximity to services & facilities and looked at public transport options in the vicinity but recognising that these are relatively limited in most villages across the National Park. In addition, the SA framework covers accessibility, movement, and car dependency. The local plan has been amended to include reference to both Hants & Wilts LTP4 and to refer to Healthy Streets and promotion of active travel. |
| JJP Planning (obo Netley Marsh Parish Council) and local residents |
The published Sustainability Appraisal (“SA”) does not demonstrate how reasonable alternatives for meeting the Travelling Showpeople requirement were assessed. Although SP50’s effects are considered within the appraisal, no equivalent comparison is identifiable for Showpeople provision. Potential alternative approaches include the consideration of other parcels of land, provision across smaller sites, and expansion or intensification of existing yards. The published assessment does not explain which approaches were considered reasonable alternatives, compare their effects or establish why reliance on LAA62 was preferred. In summary, the legal-compliance objection is that the required assessment of reasonable alternatives, and the reasons for preferring the selected approach, have not been demonstrated. |
The NFNPA has considered reasonable alternatives to meet identified need for travelling showpeople. This is evidenced by the following:
Consequently, no reasonable alternative site options were identified that required comparative assessment through the SA. |
4.4 No representations were explicitly received to the findings of the Habitats Regulations Assessment, albeit some comments were received in relation to impact of site allocations/habitat mitigation requirements and these have been summarised as part of the respective chapter summaries below.
Local Plan Chapters - Schedules of Representations
4.5 The following schedules provide an overview to the number of representations per policy, together with a summary of comments made and how the representations have been taken into consideration and whether any changes to the local plan are proposed. Where a proposed modification is considered appropriate this is shown and labelled with its reference as set out in the Submission Schedule of Proposed Modifications. Statutory consultees and known organisations are named. The schedules include data on whether policies are legally compliant and sound.
4.6 Accordingly, this statement demonstrates compliance with the requirements of Regulation 22 (1)(c) and that consultation on the preparation of the pre-submission Local Plan Review and supporting documents, including the Sustainability Appraisal, Habitats Regulations Assessment, and the submission policies map, has been undertaken in accordance with the relevant Regulations, the adopted Statement of Community Involvement (SCI) and Local Development Scheme (LDS) in place at the time.
N.B. The following schedules show total representations for each chapter/policy and, where provided, respondents’ views on legal compliance and soundness. These figures may not tally, as not all respondents answered these questions.
Local Plan Chapter: Chapter 1 Introduction and Background
- Total Number of representations received8
-
No of respondents who confirmed the policy is:Legally compliant: Yes 5 / No 1Sound: Yes 2 / No 4
| Respondent | Main Issues Raised | How the representations have been taken into account |
|---|---|---|
| Dorset Council |
Dorset Council accepts the locally derived housing needs assessment as a realistic estimate of what can be delivered within the park and therefore the Council supports the departure from the Standard Method for calculating Local Housing Need. In response to the request from NFNPA to assist in meeting housing needs, Dorset Council faces a significant housing delivery challenge itself. With regard to gypsies and travellers it is acknowledged that the NFNPA is not able to meet its own identified need through site allocations and is proposing a criteria-based policy to respond to proposals. Dorset Council similarly has a significant need for Gypsy and Traveller and Travelling Showpeople accommodation and a limited number of available sites to meet this need. It is therefore unlikely that Dorset Council will have capacity to accommodate unmet Gypsy & Traveller or Travelling Showpeople needs arising from the National Park. The Council strongly supports the protection and enhancement of the New Forest's internationally and nationally designated habitats and welcomes continued joint working on mitigating recreational impacts arising from development, and support the provision of Suitable Alternative Natural Greenspace (SANG) as part of habitat mitigation strategies within the National Park where this represents the most effective mitigation solution, including potentially for developments located outside of the Park. |
Support noted and welcomed See Cooperation Statement and Statements of Common Ground. |
| Wiltshire Council | Wiltshire Council and the NPA have maintained regular dialogue on the agreed cross-boundary issues between the two authorities. | See Cooperation Statement and Statements of Common Ground |
| Redlynch Parish Council |
Make various comments in relation to the Local Plan and supporting evidence. Key focus is strong objection to the proposed spatial strategy and major greenfield site allocations in the l parish—namely Policy SP40 (Land to the south of Hamptworth Road, Landford) and Policy SP41 (Land to the east of The Ridge, Redlynch). |
See responses under respective parts of the local plan. |
| Individual | Concern over impacts of developments and lack of infrastructure. |
Policies allocating sites for development refer to the infrastructure required and any habitat mitigation needed. See Spatial Strategy and Settlement Hierarchy Topic Papers and Infrastructure Delivery Plan. |
| Individual | Reference to "net zero with nature” in terms of making Landford a defined village will increase carbon emissions from new housing and increase car usage. | See Spatial Strategy and Settlement Hierarchy Topic Papers |
| Individual | Refers to an arbitrary 30% rule in relation to the expansion of villages and requests development should reflect need rather than an arbitrary percentage. | Unclear as to what the 30% refers to – in any event the National Park has significant development needs and new homes are needed to stabilise communities and rebalance the housing stock – see the New Forest Housing Needs Assessment (Iceni, 2025) and New Forest Housing Needs Sensitivity Report (Iceni, 2026). |
| Individual | Traditional Architecture Design Codes should be a central component across the whole local plan. | Comment noted. Policies on design and placemaking are covered by Policies DP26 Local Distinctiveness, DP27 Design Principles and DP28 Residential Character of the Defined Villages. In addition, further design guidance is available through the National Model Design Code. |
Local Plan Chapter: Chapter 2 Profile of the New Forest
- Total Number of representations received3
-
No of respondents who confirmed the policy is:Legally compliant: Yes 3 / No 0Sound: Yes 2 / No 1
| Respondent | Main Issues Raised | How the representations have been taken into account |
|---|---|---|
| New Forest Youth Board | Para 2.2 the addition of a breakdown showing the age ranges of people within the National Park would allow for a better understanding of the needs of the population. |
Agree this would add clarity to context of planning for new development in the National Park. Proposed Modification PSM5 Area and population 2.2 The New Forest National Park covers 567 square kilometres (220 square miles). In 2022 the National Park had a population of 34,931 people and with around 62 people per square kilometre it is the second most densely populated British National Park after the South Downs. In terms of population breakdown by broad age cohorts this is as follows (with comparative data for South East England) :
Renumber as 2.3 The housing stock amounts to 15,503 dwellings (New Forest Housing Needs Assessment, Iceni, 2025). The main settlements of Ashurst, Brockenhurst, Burley, Cadnam, Landford, Lyndhurst and Sway have between 1,000 and 3,500 residents. Average house prices in the New Forest are significantly higher than surrounding areas, with an average property price more than 12 times the average annual earnings. This means the New Forest has the highest average house price of any UK National Park. |
| Individual | Para 2.11 request the 3 additional Smaller Defined Villages are named | Para 2.11 sets the context for the smaller defined villages, but these are then set out in Policy SP3. No further changes are considered necessary. |
| Individual | Traditional Architecture Design Codes should be a central component across the whole local plan. | Comment noted. Policies on design and placemaking are covered by Policies DP26 Local Distinctiveness, DP27 Design Principles and DP28 Residential Character of the Defined Villages. In addition further design guidance is available through the National Model Design Code. |
Local Plan Chapter: Chapter 3 Vision and Objectives
- Total Number of representations received12
-
No of respondents who confirmed the policy is:Legally compliant: Yes 8 / No 0Sound: Yes 2 / No 7
| Respondent | Main Issues Raised | How the representations have been taken into account |
|---|---|---|
| New Forest Association | Request an additional bullet is added to para 3.4 Key Challenges making reference to the issue that the New Forest National Park has legally committed to halving carbon emissions by 2030, and to achieve net zero and net carbon sink by 2050. | Noted. Para 5.11 within the Climate Change chapter of the local plan specifically mentions this matter in this context. Paragraph 3.4 is more general and refers to ‘meeting net zero targets’. The Authority does not consider any further changes are necessary. |
| New Forest Youth Board | Reference should be made to the ensuring the socio-economic needs of young people within the National park as young people are the part of the population which will be custodians of the National Park on a longer-term basis. | Para 3.4 refers to the key challenges and covers both housing and employment matters in the context of a National Park with general references to local people – it is not considered necessary to make specific reference to young people. |
| Turley (obo Pennyfarthing Homes) |
Question the social and economic consequences of not meeting needs where there is an ageing and declining economically active population, which would preclude attainment of the local plans strategic objectives. Promote land North-East of Pennywell Gardens, New Milton for consideration. |
Application of the spatial strategy and delivery of the associated local plan allocations are considered sufficient to meet the needs of the National Park to achieve the strategic objectives expressed. Accordingly, no further sites are considered necessary. See Spatial Strategy, Settlement Hierarchy topic papers. |
| Individuals | Request deletion of Landford/Nomansland from the list of defined villages in Policy SP3. | This representation is addressed under the response to draft policy SP3 |
| Individual | Request reference to the iconic New Forest Pony is amended to read ‘protect and ensure the safety of the New Forest Pony’, due to the number being injured/killed on the roads. | Reference to the iconic New Forest Pony reflects the Special Qualities of the National Park which are a key part of implementation of the Park’s Partnership Plan which is referenced throughout the local plan, acknowledging the links between the two documents. |
| Individuals |
Changes requested to the Policies map: Defined Village Boundary for Landford, to include the area on the Lyndhurst Road, from the river Blackwater to the A36 and down the A36 from the Poacher pub to Glebe Lane. This triangle of land already has a number of industrial units and form part of the village. Cadnam - Bartley defined village to include Rose Cottage, Chinham which forms part of the built-up area within the settlement of Bartley. |
See Settlement Boundary Review Topic Paper for the rationale to the proposed settlement boundaries. |
Local Plan Policy: Policy SP1 Supporting Sustainable Development
- Total Number of representations received14
-
No of respondents who confirmed the policy is:Legally compliant: Yes 4 / No 3Sound: Yes 3 / No 5
| Respondent | Main Issues Raised | How the representations have been taken into account |
|---|---|---|
|
Lucid Planning Ltd (on behalf of Pennyfarthing Homes); Luken Beck (on behalf of Seaward Properties); Gillings Planning obo Trustees of the Barker-Mill Estates; Copythorne Parish Council; |
Support the policy approach | Support welcomed. |
| Laister Planning Ltd on behalf of Paultons Park | Support the overarching objective of SP1 and do not seek to dilute the statutory protection afforded to the New Forest National Park. But the Policy fails to recognise role of sustainable tourism in contributing to the enjoyment and understanding of the national park or the wider economic benefits, in line with the NPPF 2026. Requests criterion e) is modified to read ‘avoids adverse effects on the integrity of the protected habitats of the New Forest, including its coastline, and incorporates appropriate measures to avoid, mitigate and, where necessary, compensate for adverse impacts and to provide for habitat enhancement proportionate to the nature and scale of the development’. | The Local Plan is being submitted under the transitional arrangements and will be examined under NPPF 2024. NFNPA does not consider the changes proposed are necessary given the statutory purposes of the National Park. |
| Boyer Planning obo Taylor Wimpey UK Ltd | Question whether the local plan has identified and properly assessed the opportunities to deliver appropriate housing including from sites adjoining settlements outside the National Park. | This matter is addressed in the Spatial Strategy Topic Paper. The Sustainability Appraisal also considered ‘reasonable alternatives’ to meet housing needs, including development on the periphery. |
| Fisher German (on behalf of National Grid Electricity Transmission (NGET)) | Requests the NGET transmission assets, including overhead lines, underground cables, access routes and substations are safeguarded and to enable future network expansion as appropriate. | Noted. The Infrastructure Delivery Plan notes that National Grid at present does not indicate any major upgrade proposals within the National Park area. |
| Individual | Amend b) to refer to drought and wildfires Amend e) add reference to re-creating salt marsh to halt erosion and protect the coast |
The changes proposed are not directly linked to development and the planning system and are more appropriately addressed in other documents (e.g. the National Park Partnership Plan). |
| Individual | Include reference to ‘doctors’ in the policy. | Policy SP1 refers to in a) local infrastructure provision which would include doctors. |
| Individual | Landford/Nomansland should not be made a defined village and 'Major' development must not occur. | The responses to policies SP2 and SP3 and address the proposed settlement hierarchy and major development within the National Park. |
| Individual | The premise of sustainable development that "includes appropriate new housing to address local needs" is flawed and not fit for purpose. | The evidence on local housing needs is set out in the New Forest Housing Needs Assessment (Iceni, 2025) and New Forest Housing Needs Sensitivity Report (Iceni, 2026). |
| Individuals | Support the recognition of Cadnam-Bartley as a smaller defined villages and provision of a settlement boundary for Cadnam-Bartley is welcomed. Specific changes to the settlement boundary are requested. | Support noted. The proposed boundary for Cadnam - Bartley was reviewed in response to representations to the Regulation 18 part 2 consultation – no further changes are considered necessary. |
Local Plan Policy: Policy DP2 General Development Principles
- Total Number of representations received12
-
No of respondents who confirmed the policy is:Legally compliant: Yes 4 / No 3Sound: Yes 2 / No 5
| Respondent | Main Issues Raised | How the representations have been taken into account |
|---|---|---|
| Environment Agency | Support reference to mitigation and adaptation to climate change, including how flood resistance and resilience is incorporated into building design. | Support noted and welcomed. |
| Copythorne Parish Council | Support but question use of term ‘unacceptable’ as this is open to interpretation and how will the aims of the policy be measured objectively. | Planning decisions are made through a balanced assessment of the development plan, national policy and other material considerations. The Local Plan provides a comprehensive policy framework for making these judgements within the National Park context. |
| Brockenhurst Parish Council | All development must be appropriate & sustainable and not cause pollution. | These matters are covered by the policy. |
| Godshill Parish Council | Request the Sandy Balls Holiday Village is included as a site-specific policy. | The Authority does not consider that a separate policy for Sandy Balls Holiday Village is required. The policies within the draft Local Plan on heritage, major development, tranquillity and dark skies, holiday parks, and sustainable tourism provide sufficient policy coverage. |
| Individuals | Policy should include reference to fire and traffic matters considering local wildfire incident in summer 2026; makes no reference to cross boundary matters particularly where settlements fall within the same parish but lie outside the National Park. | Noted. Cross boundary matters are set out in the Authority’s Cooperation Statement and individual Statements of Common Ground. The Authority’s Local Plan cannot provide policy coverage for settlements outside the National Park. |
| Laister Planning Ltd on behalf of Paultons Park; Boyer Planning obo Taylor Wimpey UK Ltd | Policy DP2 should be applied proportionately to the scale, location and impacts of development. | Policy DP2 is expressed to allow for flexibility – no further changes are considered necessary. |
| Individual | Proposed site in Landford is major development and will not comply with DP2. | Allocation of the site in Landford is in response to the revised spatial strategy and the need to identify additional land for development to meet the development needs of the National Park. The local plan should be read as a whole and accordingly all policies will apply as deemed appropriate to consider planning applications, including those on allocated sites. The proposed site allocation in Landford is not considered to be major development when considered against paragraph 190 of the NPPF (2024). |
| Individual | Para 4.15 References to safer streets need to consider reduction in speed limits to 20MPH | Noted |
[Content continues through subsequent chapters and appendices in the source document.]
Appendices
Appendix A – Specific and General Consultees notified of the Regulation 19 consultation
- Mining Remediation Authority
- Historic England
- Natural England
- Environment Agency
- Marine Management Organisation
- National Highways
- National Grid
- Bournemouth Water
- Wessex Water
- Southern Water
- Hampshire & Isle of Wight Integrated Care Board
- Bath and North East Somerset, Swindon and Wiltshire Integrated Care Board
- Dorset Council planning
- Southampton City Council
- Bournemouth, Christchurch & Poole Council
- Wiltshire Council
- Hampshire County Council
- New Forest District Council
- Test Valley Borough Council
- Sir Desmond Swayne
- Sir Julian Lewis
- Christopher Chope
- Caroline Nokes
- John Glen
- Ashurst & Colbury Parish Council
- Beaulieu Parish Council
- Boldre Parish Council
- Braemore Parish Council
- Bramshaw Parish Council
- Bransgore Parish Council
- Brockenhurst Parish Council
- Burley Parish Council
- Copythorne Parish Council
- Denny Lodge Parish Council
- East Boldre Parish Council
- Ellingham, Harbridge & Ibsley Parish Council
- Exbury & Lepe Parish Council
- Fawley Parish Council
- Fordingbridge Parish Council
- Godshill Parish Council
- Hale Parish Council
- Hordle Parish Council
- Hyde Parish Council
- Hythe & Dibden Parish Council
- Landford Parish Council
- Lymington & Pennington Town Council
- Lyndhurst Parish Council
- Marchwood Parish Council
- Melchet Park & Plaitford Parish Council
- Milford on Sea Parish Council
- Minstead Parish Council
- Netley Marsh Parish Council
- New Milton Town Council
- Redlynch Parish Council
- Ringwood Town Council
- Sopley Parish Council
- Sway Parish Council
- Totton & Eling Parish Council
- Wellow Parish Council
- Whiteparish Parish Council
- Woodgreen Parish Council
- Action Hampshire
- Age Concern Hampshire
- Associated British Ports
- Bournemouth International Airport Ltd
- Calshot Activities Centre
- Campaign for National Parks
- CPRE Hampshire
- Christchurch Bicycle Club
- Community First New Forest
- Country Land and Business Association SE
- Country Land and Business Association SW
- Cranborne Chase & West Wilts Downs National Landscape
- ExxonMobil Chemical Ltd
- Federation of Small Businesses
- Friends, Families and Travellers
- Fordingbridge Society
- Forestry England
- Friends of Brockenhurst
- Friends of the New Forest
- Hampshire Chamber of Commerce
- Hampshire and Isle of Wight Wildlife Trust
- Hampshire Association of Local Councils
- Hampshire Field Club & Archaeological Society
- Hampshire Constabulary - Designing Out Crime officer
- Hampshire Fire & Rescue Service (New Forest Group)
- Hampshire Gardens Trust
- Hampshire Outdoor Centres
- Hampshire Scouts
- Homes England
- Lepe Country Park
- Lymington & District Chamber of Commerce & Industry Limited
- Lymington Harbour Commissioners
- Lymington Society
- Jackson Planning
- National Farmers' Union
- National Grid
- National Trust
- National Trust Hants & IoW
- Network Rail
- New Forest Access Forum
- New Forest Business Partnership
- New Forest Centre
- New Forest Commoners' Defence Association
- New Forest Equestrian Association
- New Forest Friends of the Earth
- New Forest Hounds
- New Forest Runners Club
- Meyrick Estate
- New Forest Sports Council
- Go New Forest
- New Forest Trust
- Ramblers Association (New Forest Branch)
- Ringwood Society
- Royal Society for the Protection of Birds (RSPB)
- Sandy Balls Estate
- Sandy Balls Holiday Village
- The Showmen's Guild of Great Britain Central Office
- The Showmen's Guild of Great Britain Western Office
- Solent LEP
- Solent Forum
- Solent Protection Society
- Southampton Airport
- Sport England
- SSE
- Swindon & Wiltshire LEP
- The Caravan Club Ltd
- Tourism South East
- Verderers of the New Forest
- Wild New Forest
- Wilts & Dorset Bus Co Ltd
- Wiltshire Association of Local Councils
- Dorset & Wiltshire Fire & Rescue
- Wiltshire Wildlife Trust
- UK Youth
- New Forest Transition CIC
- Ringwood Actions for Climate Emergency (RACE)
- Minstead Green Group
- Greener Brockenhurst
- ECO Sway
- Conservation Connection New Forest South
- Cadland Estate
- Bisterne, Pylewell & Sowley Estates
- Exbury Estate
- Somerley Estate
- Hamptworth Estate
- Beaulieu Estate
- Hinton Admiral Estate
- Pylewell Estate
Appendix B - Promotion of Regulation 19 consultation
Press releases:
Issued 10 July 2026 to 171 news outlets and community magazines, and was available to view on the Authority’s website, it received nearly 300 views: Local Plan Review for New Forest National Park - New Forest National Park
Launch of consultation: Have your say on the draft New Forest National Park Local Plan - New Forest National Park
Media coverage:
- Local Plan Review for New Forest National Park - New Forest National Park
- Next steps taken for New Forest National Park Local Plan | Daily Echo
- The draft NPA Local Plan will be considered by authority members next week
- New Forest National Park Local Plan six-week consultation | Bournemouth Echo
- New Forest National Park Local Plan six-week consultation | Salisbury Journal
- Residents invited to have their say on draft New Forest National Park Local Plan - Yahoo News UK
- Have your say on the draft New Forest National Park Local Plan - Netley Marsh
- New Forest National Park Draft Local Plan | Landford Parish Council
Park Life newspaper:
Park Life is produced twice a year, in conjunction with the Lymington Times. Copies were distributed together with the Lymington Times, to visitor attractions.
A digital version was also made available on the National Park website.
Readership for Spring/Summer 2026 edition 56,250
Newsletters:
Enews (27,000 subscribers)
Sent 11 August:
Sent 27 August:
Sent 11 September:
Facebook banner displayed during the consultation:
Poster:
Sent to all local towns and parishes and displayed in notice boards around the New Forest
On-line session and Drop in Events:
An online presentation and consultation event was held via Microsoft Teams on Thursday 10 September 2026, between 4pm – 5.30pm.
Drop-in Events:
| Location | Date |
|---|---|
| Landford Village Hall | Wednesday 2 September 2026 |
| Bartley Village Hall | Friday 4 September 2026 |
| The Copythorne & District Royal British Regional Hall | Monday 7 September 2026 |
| Jubilee Field, Sway | Tuesday 8 September 2026 |
| Lyndhurst Community Centre | Friday 11 September 2026 |
| Redlynch Village Hall | Wednesday 16 September 2026 |
All drop-in sessions were structured as follows:
- 2pm-5pm - view the display boards and chat informally with National Park Authority officers about the revised draft Local Plan.
- 5.30pm Presentation explaining the key changes since the 2025 consultation and the next steps for the Local Plan, followed by a managed Q&A session.
Social media:
31 published posts across NPA Facebook channels, including Facebook, X, LinkedIn and Instagram.
An average engagement rate of 3.9% was achieved, which is well above the local government average of 1.1%
Total
Appendix C - Public notice