RAPC 600/26 – First Quarter Progress Report 2026/27 – Annex 1
Summary
Document Viewer
Annual Work Programme 2026/27 – First Quarter (1 April to 30 June 2026)
RAPC 600/26
Annex 1,
Re:New Climate - Net Zero with Nature
We understand the impacts of climate change on the special qualities of the New Forest National Park; we take the action needed to adapt to build resilience of the special features and we strive to drive down emissions to be a net-zero landscape by 2050.
Protected Landscapes Targets and Outcomes Framework targets for the Landscape (PLTOF):
- Net zero greenhouse gas emissions by 2050
- 20 hectares of peat restoration by 2050
- 550 hectares of new woodland and tree cover by 2050.
| Outcomes | Actions / Priorities | Quarterly RAG Status | Achieved by March 2027 | Action to regain (if amber or red) | Particular points to note |
|---|---|---|---|---|---|
| Establishing baseline data & evidence (Paul Walton) |
|
Point 2: Amber due to likely timings of Landscape Observatory work which may not be in time to fully inform the PP. | |||
| Increase sustainable transport (Jim Mitchell) |
|
||||
| Motivating climate action (Paul Walton) |
|
||||
| Organisational net zero (Nigel Stone) |
|
||||
| Increasing natural capital (Paul Walton) |
|
Re: New Nature - Nature Recovery
Nature is restored, enhanced and connected to boost biodiversity and improve ecosystem health
PLTOF targets for the landscape:
- Increase wildlife-rich habitat by 4000 hectares by 2042 from 2025
- 80% of SSSIs in favourable condition by 2042
- 60% of SSSIs have ‘actions on track’ by 2042
- More priority habitats supported by agri-environment schemes
- 65% of land managers adopting nature-friendly farming.
| Outcomes | Actions / Priorities | Quarterly RAG Status | Achieved by March 2027 | Action to regain (if amber or red) | Particular points to note |
|---|---|---|---|---|---|
| Making space for nature: Increase the amount of land managed for nature contributing to the 250ha annual target and identified improvements to the New Forest Sites of Special Scientific Interest (Paul Walton) |
|
||||
| Better understanding of the level of financial investment in nature in the National Park (Paul Walton) |
|
Point 1: Remains a critical piece of work for the New Forest community to solve ahead of HLS funding ending. | |||
| Enabling nature recovery in the National Park (Paul Walton) |
|
The NFNPA is working with partners to explore the feasibility of introducing an LDO for nature recovery projects (focusing on wetland restoration) | |||
| Engaging people in nature (Hilary Makin) |
|
||||
| Protecting nature (Paul Walton) |
|
The Regulation 19 Submission draft Local Plan will be subject to further consultation between August – September 2026. |
Re:New People - An Inclusive National Park
The benefits provided by the New Forest National Park are accessible to all who wish to enjoy them
PLTOF targets for the landscape:
- Increased accessible paths, toilets, rest stops, parking spaces, routes, gates and gaps by 2042
- Increased visits & volunteer days facilitated by new equipment by 2042
- Increased number of schools and volunteers engaged by 2042
| Outcomes | Actions / Priorities | Quarterly RAG Status | Achieved by March 2027 | Action to regain (if amber or red) | Particular points to note |
|---|---|---|---|---|---|
| Inclusive volunteering helps deliver National Park purposes (Jim Mitchell) |
|
||||
| Accessible routes are delivered (Jim Mitchell) |
|
||||
| Enable more people to engage with the National Park and to have a say in its future (Jim Mitchell) |
|
||||
| PEDALL inclusive cycling and other health opportunities are delivered (Jim Mitchell) |
|
||||
| Develop and deliver high-quality, bespoke curriculum linked education for schools and colleges (Jim Mitchell) |
|
Re:New Place - Thriving Forest
The interdependence between economic growth and the unique natural beauty and cultural heritage of the landscape underpins a sustainable future for the New Forest National Park
PLTOF targets:
- Decreases in numbers of scheduled monuments and listed buildings ‘At Risk’ by 2042
| Outcomes | Actions / Priorities | Quarterly RAG Status | Achieved by March 2027 | Action to regain (if amber or red) | Particular points to note |
|---|---|---|---|---|---|
| Ensure economic and social objectives for our area informed by and contributing to the natural capital of the National Park working through the Green Halo Partnership, the Greenprint Framework and relationships with key partners (Paul Walton) |
|
||||
| Support sustainable land management and securing the future of Commoning (Paul Walton) |
|
Point 1: Amber – our work on this remains critical to achieveing the post-HLS funding & investment needed for Commoning into the future. | |||
| Improve data and oversight of land use change in the National Park to inform land use decisions (Paul Walton) |
|
Archaeology team has two temp staff, likely to recruit to perm role soon. | |||
| The New Forest National Park continues to be covered by an up-to-date planning policy framework (David Illsley) |
|
Hampshire Minerals & Waste Plan adopted July 2026 | |||
| Grow awareness of and opportunities to develop green skills and careers amongst the New Forest workforce (Jim Mitchell) |
|
Re:New Partnership - Team New Forest
Everyone involved in advancing the Purposes of the National Park works together with trust, respect, inclusion and innovation.
| Outcomes | Actions / Priorities | Quarterly RAG Status | Achieved by March 2027 | Action to regain (if amber or red) | Particular points to note |
|---|---|---|---|---|---|
| Consultation draft of New Forest National Park Partnership Plan review complete (Strategic Leadership Team) |
|
. | |||
| Community feedback (Hilary Makin) |
|
||||
| Shared experiences through Team New Forest (Nigel Stone) |
|
Re:New Organisation - Achieving Excellence
We lead by example; we strive to improve; we are dedicated to maximising value from public funding; we have a strong dedication to customer service; we are an engaged, motivated, safe and inclusive workforce
PLTOF targets for the landscape:
- Policies in place to ensure positive action to widen the diversity of staff, board and volunteers
| Outcomes | Actions / Priorities | Quarterly RAG Status | Achieved by March 2027 | Action to regain (if amber or red) | Particular points to note |
|---|---|---|---|---|---|
| Capital grants programme delivered (Nigel Stone) |
|
||||
| Sustainable finances and facilities (Nigel Stone) |
|
||||
| Provide effective and creative communications to drive behaviour change and create greater awareness, ensuring they are accessible and inclusive (Hilary Makin) |
|
||||
| Develop & Support Members role (Chair & Nigel Stone) |
|
||||
| People Plan Reviewed and Enacted (Nigel Stone) |
|
Staff survey delayed until after Summer break. | |||
| Equality, Diversity and Inclusion is embedded across the organisation (Jim Mitchell) |
|