April 2026- Local requirements proposed changes
Summary
Document Viewer
NEW FOREST NATIONAL PARK AUTHORITY
LOCAL LIST REQURIEMENTS
Adopted on
| Document types | When Required (proportionate approach is taken as to level of detail in each particular case): | Policy References | Where to look for further assistance |
|---|---|---|---|
| Additional Plans |
The national requirements note the need for a location plan and “others as necessary” with a reliance on the local requirements to detail what those are. For the avoidance of doubt, the local requirements should confirm what we need (particularly for the local requirement of calculating floorspace):
|
|
NFNPA Website |
| Affordable Housing Statement |
Required for all new residential development of 3 or more units or where the floor space of the proposed housing would exceed 1,000 square metres and for all applications for Rural Exceptions Sites under Local Plan Policy SP28 and NPPF paragraph 78. |
|
NFNPA Website |
| Agricultural and Forestry/ Estate Worker/ Commoner’s Dwelling Statement |
Required for proposals for agricultural/ forestry/ estate worker’s or commoner’s dwellings and all new agricultural buildings. Agreement to payment of fee for independent verification of statement. |
Local Plan Policy DP31 | NFNPA Website |
| Air Quality Assessment |
Required for any development affecting Lyndhurst Air Quality Management Areas (AQMAs) or where the development could lead to the designation of an AQMA with high levels of pollution. |
|
|
| Arboricultural Implications Assessment |
Required for all applications that include or are likely to affect Ancient and Semi Natural Woodland |
|
|
| Archaeological Desk-Based Assessment |
Required for all major planning applications. All statements and documents must meet industry standards. |
|
NFNPA Website |
| Biodiversity Survey and Report |
Biodiversity checklist required for all applications. Ecology Surveys required for all applications for development within, adjacent or within close proximity to international, national or local nature conservation sites unless the Authority advises otherwise. Preliminary Ecological Assessment (including Potential Bat Roost Assessment) required for any development involving demolition or changes of a structure or changes to roof and cladding structures including fascias, soffits, hanging tiles and weather boarding. |
|
|
| Biodiversity Net Gain Requirements |
When a planning application is submitted, there are minimum national information requirements related to biodiversity net gain for those applications which, if planning permission was granted, would be subject to the general biodiversity gain condition. This will allow consideration of existing habitat baselines. The existing on-site habitat plan to be submitted under national requirements must also include an accurate scale bar and page size. The Authority may also seek further information about the proposed strategy to meet the biodiversity gain objective for the development. This would not apply to the following exemptions:
|
|
Biodiversity net gain - GOV.UK (www.gov.uk) |
| Construction management statement |
Required for all applications within or immediately adjacent to SSSI or Ramsar, SAC or SPA areas |
|
Natural England Website |
| Design and Access Statement |
Required for all applications for major development; applications in a conservation area consisting of 1 or more dwellings or buildings of 100+ square metres. Required for applications for listed building consent. |
National Planning Policy Guidance Paragraph 030 (“Making an application-Design and Access Statement”) | NFNPA Website |
| Flood Risk Assessment (FRA) |
A site specific flood risk assessment should be provided for all development in Flood Zones 2 and 3. This includes householder development, small non-residential extensions (with a footprint of less than 250 sq. m) and changes of use; except for changes of use to a caravan, camping or chalet site, or to a mobile home or park home site, where the sequential and exception tests should be applied as appropriate. In Flood Zone 1, an assessment should accompany all proposals involving: sites of 1 hectare or more; land which has been identified by the Environment Agency as having critical drainage problems; land identified in a strategic flood risk assessment as being at increased flood risk in future; or land that may be subject to other sources of flooding, where its development would introduce a more vulnerable use. |
|
|
| Heritage Statement (including Historical, Archaeological features and Scheduled Ancient Monuments) |
Required for all applications affecting designated and non-designated heritage assets (including historic parks and gardens, battlefields and Scheduled Ancient Monuments and non-scheduled archaeological sites, areas of significant archaeological potential and areas with the potential to impact on heritage assets with archaeological interest). Required for all applications within and adjacent to Conservation Areas, including demolition of non-listed buildings within Conservation Areas. Required for all applications affecting Listed Buildings including works and buildings within the curtilage of a listed building. Required for all applications in Conservation Areas and within the curtilage of a listed building that include excavations. Reference to the Historic Environment Record is expected as a minimum. The statement should include: an assessment of the heritage asset’s significance; discuss the impact of the proposal on the heritage asset and its significance; and a statement of how harm has been avoided or minimised through design mitigation. Statements must include internal and external photographs and a construction method statement giving details of appropriate working methods and practices. |
|
|
| Land Contamination Assessment |
Required where contamination is known or suspected to exist or the proposed use is vulnerable and is included on the list of contaminated sites. Within 250 metres of a currently licensed or historic landfill site. |
|
|
| Landscape Statement |
Required for major development where existing trees, hedges and other landscape features will be affected by the proposals and landscape needs to be considered as an integral part of the development. Proposals should include details of proposed soft & hard landscape, and its long term maintenance. A Landscape Visual Impact Assessment (LVIA) is required for larger applications and/ or applications in particularly sensitive locations. New Forest National Park Landscape Character Assessment and Landscape Action Plan. |
|
NFNPA Website |
| Lighting Assessment/ Lighting Information |
Required for all proposals involving large areas of external lighting (lit car parks, floodlighting of buildings, structures or areas). For small scale lighting/ development, lighting information including Lux levels and the design of the lighting units. For large scale lighting/ development, a full assessment should be provided including a full external lighting plan with Lux levels with a Lux contour map, the design of the lighting units and potential impact/ mitigation. |
|
|
| Nutrient Mitigation Information |
Nutrient Mitigation Checklist and relevant Nutrient Budget calculation required (Solent or River Avon) for applications proposing a net increase in dwellings or other forms of overnight accommodation. |
|
|
| Noise Assessment |
Required for any major development where it is likely to generate associated noise or activity in noise sensitive areas. |
|
|
| Planning Obligations- Draft Heads of Terms or Draft Unilateral Undertaking (for smaller scale applications) |
Where off-site contribution is required and is to be provided, this should be submitted with the planning application and where Local Plan Policies/ SPD give details of likely requirements. Statement must confirm willingness to pay in full or provide details of on-site ecological mitigation measures instead. |
|
|
| Statement of Community Involvement | Required for all major applications. |
National Planning Policy Framework Section 4 | |
| Surface Water Drainage Statement | Required for all major applications. |
National Planning Policy Framework Section 14 | Hampshire County Council Website |
| Sustainability Statement |
Required for all planning applications. The statement should include details of how the proposal is resilient and responsive to the impacts of climate change through: improved energy efficiency; making appropriate use of small-scale renewable energy; its use of sustainable building techniques, local materials and minimising energy use and waste; water efficiency; and enabling wildlife and habitats to adapt to climate change. |
|
|
| Telecommunications Development - Supplementary Information | Required for all Telecommunications applications. |
National Planning Policy Framework Section 10 | |
| Transport Assessment | Required where proposal would lead to significant transport implications. |
|
|
| Travel Plan | Required for all planning applications where a Transport Assessment is required. |
|
Hampshire County Council Website |
| Tree Survey/Arboricultural Implications Assessment | Required for all applications where trees or hedgerows are proposed to be lost or would be affected (directly or indirectly) by the development. |
|
NFNPA Website |
| Ventilation/Extraction Statement | Required for applications for uses involving food preparation – restaurants, cafes, takeaways and pubs (parts of Class E and Sui Generis categories of the Use Classes Order as amended 2020). |
|
NFNPA Website |
| Viability Appraisal | Required for all applications for new dwellings where the applicant is seeking relaxation from contribution requirements. |
Local Plan Policy SP38 | NFNPA Website |